Schedule Update — Yellow Section 11/17/25

Schedule update from Cadillac

Monday 11/17 paving

With the delayed start this morning waiting for temps to warm up, Cadillac was able to pave just the northern block on Glengarry, starting at Quarton and working south. The paver will finish for the day just south of the intersection with Glengarry Circle and Sandringham (the north intersection with the Circle). Because tack has been sprayed on the block between the north and south intersections with the Circle, Cadillac will leave the barricades up this evening.

Tuesday 11/18

The weather forecast for Tuesday 11/18 is likely too cold for paving in the Indian Mound area as scheduled. Cadillac is deferring Indian Mound paving until Wednesday. They were able to pave Indian Mound Trail and the west entrance today. Stay tuned for the revised schedule for the remainder of the week.

Wednesday 11/19

Paving:

  • Cadillac will start on Glengarry and pave the remaining area not completed on Monday (block between the north and south intersections with the Circle).

  • After Glengarry, Cadillac will move into the Indian Mound area. Paving will start on Indian Mound South and work north into Indian Mound West and around the square.

  • The weather forecast indicates there will likely be a delayed start on Wednesday before the temperature is warm enough for asphalt. It is likely that Cadillac will not finish the Indian Mounds on Wednesday and paving would continue on Thursday.

Thursday 11/20 (tentative)

  • Complete paving on the Indian Mounds.

  • Driveways on Sandringham/cul-de-sacs and Indian Mounds

Friday 11/21 (tentative)

  • Finish driveways.