Construction Update — Yellow Section 11/19/25
Construction update from Cadillac
Wednesday 11/19
Cadillac has paved the second layer of asphalt on the remainder of N. Glengarry, starting where they left off Monday, and moved to Indian Mound S and Indian Mound West. They will continue paving along the north side of the square, moving clockwise toward the Covington entrance. The west entrance off Glengarry Circle East has been opened for traffic.
Thursday 11/20
Cadillac will pick up paving where they left off on Wednesday, probably somewhere on the north side of the Indian Mound square. Indian Mound East, Indian Mound Road and the Covington entrance will be closed to all traffic and parking on Thursday for paving. Residents can park on Indian Mound West or Indian Mound South and use the Glengarry Circle East entrance to the area.
After paving is completed, Cadillac will shift to asphalt driveways, starting on Sandringham and the cul-de-sacs.
Fort Wayne will be adjusting structures (manholes) in the roadway on N. Glengarry.
They will remove asphalt that covers each structure, adjust the height to be flush with the pavement, and install a concrete collar around the structure.
This work will likely block the road where Fort Wayne is working. There will be flaggers to direct residents to detour around the work. Residents should avoid N. Glengarry, particularly the first block off Quarton, on Thursday. Detour on Sandringham instead.
Avoid parking on the street on N. Glengarry Thursday, to reduce congestion and stay out of Ft. Wayne’s way.
Mike’s Landscaping continues restoration work, including resetting bluestone front walks, topsoil and sod in remaining construction-damaged areas. Bluestone work should be completed this week; topsoil and sod will continue for several weeks.
Friday 11/21
Cadillac will continue pouring asphalt driveways until all are completed. They will be working in the Indian Mound area and finishing anything left from Sandringham and the cul-de-sacs. This work will continue into Saturday.
Fort Wayne will be completing structure adjustments in the Indian Mound area, Sandringham and the cul-de-sacs. As indicated above, Fort Wayne may block the road during this work and require traffic to detour around it. Please refrain from parking in the street to allow Fort Wayne room to complete this process.
Saturday 11/22
Cadillac will complete remaining asphalt driveways.
Week of 11/24
Doan will complete remaining open concrete work.
Owen’s Tree Service will be removing two trees at the corner of Sandringham and Glengarry on Tuesday and Wednesday. The roots of the trees have been badly damaged by construction of both the underdrain/curb and the required ADA ramps on the adjacent sidewalks.
Mike’s Landscaping will continue topsoil/sod work around driveways, ADA ramps and other more recently completed work. Mike’s will likely be back the week of 12/1 for final restoration work.
Looking ahead
In the next few weeks, construction signage and portable toilets will be removed from the construction zone, as the construction crews clear out for the winter.
Mike’s Landscaping will be back in the spring for repairs to sprinklers they were not able to complete/test this fall. They will also replace sod if it has not rooted by the time they leave the area this fall. Mike’s will not replace normal wear/tear on landscaping this winter — areas damaged by the plow, sod parked on/driven over during the winter, damage caused by other contractors, and the like.
Additionally, lining of structures in the roadways will be completed in the spring.