Schedule Update — Yellow Section 11/10/25
Schedule Update from Cadillac
***** All planned timing is weather dependent *****
Tuesday 11/11
Miller Brothers will be profile milling in the Indian Mound area, on Glengarry Circle East, the southern part of Sandringham, and segments of N. Glengarry (1322 to 1440 N. Glengarry and 932 to 1052 N. Glengarry). Profile milling is done where the first layer of asphalt is more than the standard 2.5 inches thick and thus doesn’t leave enough room for the second layer. The mill removes limited amounts of the first layer of asphalt to result in a consistent 1.5 inches of space between the first layer and the curb height. The second and final layer of asphalt will be laid at 1.5 inches thick. (Total thickness of asphalt upon completion will be 4 inches — 2.5 inches for the first layer plus 1.5 inches on the second layer.)
Miller Brothers will also be removing 3 small areas of the asphalt base for repair on Indian Mound East (near 1296 and 1274 IME), Indian Mound South (near 2723 and 2709 IMS) and Indian Mound Road at Glengarry Circle East.
No parking on the street in the Indian Mound area or Glengarry Circle East on Tuesday. Street parking on Sandringham north of Twin Maples is fine. Avoid the areas on N. Glengarry where milling will be done. Your best option is to park in your driveway or arrange with a neighbor to park in theirs. You will have access to the street, although there may be temporary delays.
Wednesday 11/12
Driveways — Cadillac will start with base asphalt layer on Glengarry Circle East, then move into the Indian Mound area for base layer on 12 drives left there. Once every drive has a base coat, they will pour as many top layers as they can. Most likely, drives that aren’t finished on Wednesday will be done next week, after the final layer of asphalt paving is done throughout the Yellow (and Gold) section.
If you are getting an asphalt drive, plan to be out of the driveway for the day.
Parking suggestions — arranging with a neighbor to park in their driveway is the best option. Otherwise, Indian Mound West is a good option (stay away from 1250 Indian Mound West) or Glengarry Circle East (north of 950 Glengarry Circle East) or the part of Indian Mound South that is not in the Village. Avoid Indian Mound Road and Indian Mound East as there are lots of driveways to be done there. If you have to park in the street in other parts of the area, leave room between your vehicle and any driveway that isn’t done yet.
Thursday 11/13
Paving in Indian Mound area - Cadillac will start with base repairs in the 3 spots milled on Tuesday. Stay tuned for the order on the rest of Indian Mound streets.
Friday 11/14
Finish paving in Indian Mound area.
We have requested that Priority Waste postpone garbage pick-up in the Indian Mound area until Monday 11/17. We will post on the blog when we have confirmation.
Saturday 11/15
Paving on Glengarry Circle East (starting at south end and moving north).
Start paving on N. Glengarry (start at south end, move north toward Quarton).
Monday 11/17
Finish paving on N. Glengarry
Paving on cul-de-sacs
Paving on Sandringham (moving south to north).
Access limitations during paving, parking suggestions