Gold Section - Milling Update 9/18/25

The milling crew started on Hamilton this morning instead of Glengarry, and encountered some unanticipated issues. The crew will be back tomorrow to finish any remaining areas on Hamilton, then move over to Glengarry. We expect Cadillac to communicate an update on timing for milling on Williamsbury and Morningview sometime tomorrow afternoon.