Gold Section — Change in Curbing Schedule, Early Start Times

Changes to curbing schedule

Cadillac has informed us that Doan plans to lay curbs this afternoon and Saturday 7/26 on Morningview (pink area on the map below), which is a change in the order they previously communicated. All impacted residents on Morningview have been notified.

The orange and green areas (Cliftons, Chewtons) are scheduled for curbs on Monday 7/28. Notices have been placed on front doors to notify impacted residents.

Early start times next week

Bloomfield Township has given permission for early start times for the curb contractor on Monday next week, in recognition of the projected high temperatures early next week. Crews will arrive at 6 am and concrete pouring will begin at 7 am.