Blue and Pink Section Restoration Work Update
Pink and Blue Sections — Restoration Work
Comparative Data for Pink, Blue, Yellow and Gold Sections
Restoration Work in Blue Section
Construction Update - Pink and Blue Sections - 12/4/24
Construction update — BLUE section 11/6/24
BLUE section - No parking on Half Moon on Thursday 11/7/24
Paving in Blue section - weeks of November 4 and 11
Construction update — BLUE section 10/30/24
Road construction update — BLUE section 10/23/24 (with revised paving dates)
Paving in BLUE section moved to Thursday/Friday this week
Construction Update — BLUE section 10/17/24
Revised milling schedule for week of 10/14/24 — PINK and BLUE sections
Construction update — BLUE section 10/9/24
Construction Update — Blue Section 10/2/24
BLUE section revised paving schedule - week of September 30
Curbing and Paving in the BLUE section — week of September 30
Construction Update — Blue section 9/25/24
How are Village Roads projects put out to bid?